Quarterly Construction Update October 2018

Alliance Project Group has been appointed as the Builder for Stellar.

In recent months, excavation and installing the retaining walls have been the focus. The basement is now taking shape, as are the footings, columns and services for the basement levels.

The suspended slab and the other basement levels are expected to be constructed in the coming months.

CWG and Alliance Project Group have been working with authorities to improve the area surrounding the site including landscaped areas and artwork, so as to enhance the environment for Stellar’s residents and visitors.

More updates are expected to be available in January 2019.

Quarterly Construction Update July 2018

Over the last few months, CWG Development has been working with its consultants and builder towards finalising the design and reports for the first construction certificate. This was received at the end of June 2018 and the builder has now commenced onsite.

Prominent Australian artiste Jade Oakley has been engaged to create artwork for Stellar. CWG along with Jade Oakley, publicArt.works, Alliance Project Group and Ryde City Council will be working closely to procure artwork for when construction is complete.

Currently, hoarding and temporary fencing have been installed ready for the excavation of the basements. The site sheds are located just off Belmore Lane, which is near the access points for the vehicles entering and exiting the site. In the months ahead, ground works are planned on site. Keep an eye out for excavation, piling, inground services installation and footing installation.

Quarterly Construction Update Jan 2018.

Site establishment commenced in early December 2017 including demolition of the existing building, basement floors and general cleaning and preparation for the main demolition works.

Main Demolition commenced mid-December 2017 with the demolition of the existing building and now, demolition of the ground floor slab.

As demolition progresses, barrier protection such as mesh fencing and scaffolding is being coordinated in order to maintain a safely secured site.

Dust control measures also consistently in operation.

Completion of demolition works is expected to be in March 2018.

More Updates will be available in July 2018.

Privacy Policy

This statement discloses the privacy practices for the entire Stellar website.
Questions regarding this statement should be directed to info@chiwaylandau.com. We respect the privacy of our customers and therefore have adopted a set of information management guidelines that are the foundation of our customer relationships. These guidelines have been developed with the recognition that internet technologies are rapidly evolving and that underlying business models are still not established. Accordingly, guidelines are subject to change. Any such changes will be posted on this page as required.

What we do
We collect personally identifiable information about our users. Our goal in collecting personal information online is to provide you with the most useful and helpful web experience possible. By knowing your preferences, we will be able to deliver information that meets your needs and gives you special access privileges. Through online forms, we collect:

We use this information for the following purposes:

What we don't do
We do not, under any circumstances:

Upon request, we will remove any subscriber (and his or her personal information) from our mailing lists. Any such request should be sent via email to info@chiwaylandau.com
CWG is not responsible for the content or the privacy policies of external web sites to which we may link.

Disclaimer

Please note the material contained herein has been produced prior to detailed design and construction, is indicative only and does not constitute a representation by the Vendor, Agent or Vendor’s consultant in respect to the size, form, dimensions, specifications or layout of the apartment or at all. The final product may change from that illustrated herein. Furniture is not included. All furniture shown is for illustration purposes only. Changes may be made to the detail layouts during the development in accordance with the provisions of the contract of sale or the building and or planning requirements or for compliance with relevant standards or codes. Prospective purchasers must make and rely on their own enquiries.